Respuesta :
Set up a proportion of acres to days. 1/2 acre is to 4 days as 2 3/4 acres is to x days.
x= # days to clear 2 3/4 acres
2 3/4 to improper fraction= 11/4
(1/2)/4 = (11/4)/x
cross multiply
(1/2 * x) = (4 * 11/4)
on the right, the 4 "cancels out"
1/2x= 11
divide both sides by 1/2
x= 11 ÷ 1/2
to divide fractions, multiply by reciprocal/inverse of 1/2
x= 11 * 2/1
x= 22 days
ANSWER: It would take 22 days to clear 2 3/4 acres.
Hope this helps! :)
x= # days to clear 2 3/4 acres
2 3/4 to improper fraction= 11/4
(1/2)/4 = (11/4)/x
cross multiply
(1/2 * x) = (4 * 11/4)
on the right, the 4 "cancels out"
1/2x= 11
divide both sides by 1/2
x= 11 ÷ 1/2
to divide fractions, multiply by reciprocal/inverse of 1/2
x= 11 * 2/1
x= 22 days
ANSWER: It would take 22 days to clear 2 3/4 acres.
Hope this helps! :)
The first think we presume: it is 2 3/4 acres more and does not include the 1/2 acre they have already cleared.
Then it is a ratio equation problem. I change fractions to decimal equivalents.
So you set 0.5 acres / 4 days and 2.75 acres / n days
Then multiply means and extremes
4(2.75) = 0.5(n)
11 = 0.5(n) divide both sides by 0.5 to get n alone
11/0.5 = n solve for n
22 = n
It will take the same crew 22 days to clear 2 3/4 more acres.
Then it is a ratio equation problem. I change fractions to decimal equivalents.
So you set 0.5 acres / 4 days and 2.75 acres / n days
Then multiply means and extremes
4(2.75) = 0.5(n)
11 = 0.5(n) divide both sides by 0.5 to get n alone
11/0.5 = n solve for n
22 = n
It will take the same crew 22 days to clear 2 3/4 more acres.