Respuesta :

The cumulative budgeted cost at the end of week 6 is $100,000. The answer in this question whose are amounts are in thousand of dollars is $100,000. So, the cumulative budgeted cost at the end of the week 6 is $100,000.Cumulative budgeted cost or acronym of CBC is the amount that is budgeted in order to accomplish the work that was scheduled.