PERT is a review technique/tool, so that can't be it. CPM is Critical Path Method, and you can use a PDM or an ADM to chart it.
The easy way to remember this answer, is that you write on the arrow when using the "arrow diagram method."
So the answer is "a. pdm" (precedence diagram method).