A crew is building 13 miles of road. they complete half a mile every week. what is the equation for figuring out how long it will take to complete?

Respuesta :

Let x be the weeks worked on building the road

13=(1/2)x
13*2=x
26 days=x

In the duration of 26 weeks, the road should be built.