Those paths with positive values of total slack are sometimes referred to as noncritical paths.

The amount of time a task can float, also known as slack, before colliding with another job. When you schedule tasks, it is automatically added to your project, and you can utilize it as a buffer period if necessary if your schedule is in danger of running behind.

Total slack is the maximum amount of time that a work may be put off before the project's completion date is also put off. Total latitude may be advantageous or harmful. The length of time that the task may be put off without pushing back the project's completion date is indicated by a positive slack. Total slack, if negative, is the amount of time that needs to be saved in order to keep the project's completion date on schedule. Non critical path activities have positive slack.

Learn more about slack here: