The time it will take the second crocodile to finish it's snack is; 120 s
What is the rate of finishing work?
Let x represent the rate of the first crocodile and let y represent the rate of the second crocodile.
The two crocodiles working together can finish a snack in 40 seconds. Thus;
(1/x + 1/y)40 = 1
It takes one of the crocodiles 60 seconds to finish it's snack. Thus;
(1/x + 1/60)40 = 1
40/x + 2/3 = 1
x = 120 seconds
Read more about rate of work at; https://brainly.com/question/12442233