Respuesta :
Answer:
For comprehension purposes, I would write the question again with options attached below:
Agile project management involves ____ whereas traditional project management involves _______. Multiple Choice
a. known and stable scope, unknown requirements
b. high certainty, projects with unstable scope
c. projects with high predictability, project with unknown or unstable requirements
d. iterative and incremental delivery, upfront planning with high predictability
e. high uncertainty, projects with unknown requirements
The correct answer is option d. (iterative and incremental delivery, upfront planning with high predictability)
So, Agile project management involves iterative and incremental delivery whereas traditional project management involves upfront planning with high predictability.
Explanation:
Agile project management involves iterative and incremental delivery as Agile project management allows making changes to the product which then opens ways for iteration. Agile life cycles are composed of several iterations because of changes that might arise due to feedback during the production process of the project.
Traditional project management is highly predictable and it doesn't give room for changes as project cycles and stages are planned ahead. It's a rigid process.
According to business strategy, Agile project management involves iterative and incremental delivery,
whereas traditional project management involves upfront planning with high predictability.
What is Agile Project Management?
Agile Project Management is a style of business or production management that allows the production process to be changed accordingly throughout the process till final delivery or life cycle.
On the other hand, traditional project management is a style of project management that ensures the proper planning is done with preparation for uncertainty made at the planning stage; thereby, little or no adjustment is made till final delivery or project cycle.
Hence, in this case, it is concluded that the correct answer is option C. "iterative and incremental delivery, upfront planning with high predictability."
Learn more about project management here: https://brainly.com/question/988326