The delivered equipment cost for setting up a production and assembly line for high-sensitivity, gas-damped accelerometers is $650,000. If the direct cost and indirect cost factors are 1.36 and 0.31, respectively, and both factors apply to delivered equipment cost, the total plant cost estimate is approximately:______

a. $2,034,500
b. $1,815,500
c. $1,735,500
d. $1,183,000