Answer:
Predetermined manufacturing overhead rate= $391.78 per direct labor hour
Explanation:
Giving the following information:
Budgeted factory overhead= $2,948,125.
Direct labor hours:
Flutes= 2,000*2= 4,000
Clarinets= 1,500*3= 4,500
Oboes= 1,750*1.5= 2,625
Total direct labor hours= 7,525
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 2,948,125/7,525
Predetermined manufacturing overhead rate= $391.78 per direct labor hour