Scope creep refers to: a. a task at the lowest level of the WBS. b. the approved project scope statement and its associated WBS. c. subdividing project deliverables into smaller pieces. d. the tendency for project scope to keep getting bigger and bigger.

Respuesta :

Answer:

The Answer is d. the tendency for project scope to keep getting bigger and bigger.

Explanation:

A scope  refers to all the work involved in creating the products of the project and the processes used to create them.

A scope creep refers to changes, continuous or uncontrolled growth in a project's scope, at any point after the project begins. This can occur when the scope of a project is not properly defined, documented, or controlled.

Hence the answer is d. the tendency for project scope to keep getting bigger and bigger.