One of the main outputs of the initiation process is _____. a. selecting the project manager b. developing the project charter c. creating the work breakdown structure d. identifying the project sponsor

Respuesta :

Answer:

The most suitable answer is b. developing the project charter

Explanation:

You might say that selection of a manager is true as well. In that case, yes it is. But it is not the MAIN OUTPUT, the main output us terms charter which states what to do and what we are expecting to do. Moreover, the charter points out in detail the plan, the funding, sponsors, responsibilities, etc.