The marketing team would develop the advertising campaign to promote the newest product but the engineers wanted to keep all product details a secret during development. The service and operations branches of the company were also in the dark, so product rollout was going to be their initiation as well. This project has a very high:

A) Political risk.
B) Operating risk.
C) Organizational risk.
D) Integration risk.